MJS工法超长高压旋喷桩在深基坑止水工程中的应用

作者:刘澄赤 卞睿凡 睢博栋
单位:浙江省地矿建设有限公司 同济大学土木工程学院
摘要:以上海瑞虹新城10号地块发展项目为依托,对MJS工法超长高压旋喷桩在深基坑止水工程中的应用进行研究。结合MJS工法施工工艺原理,总结该工法应用于超深土层时的施工特点与关键控制要素。现场试桩试验结果表明,MJS工法超长高压旋喷桩成桩质量较好,在20m深度处成桩直径可达2.55~2.80m,且桩身无侧限抗压强度>1.3MPa;止水加固施工对周围土体的影响较小,施工引起的地表竖向位移<2.22mm、距试桩边界6m处深层土体最大水平位移<4mm。
关键词:深基坑高压旋喷桩止水帷幕MJS工法施工技术
作者简介:刘澄赤,硕士,工程师,E-mail:983674080@qq.com。
基金:杭州市科技计划项目(2017028)。 -页码-:85-87
尊敬的用户,本篇文章需要20元,点击支付交费后阅读
参考文献[1] NJOCK P G A,CHEN J,MODONI G,et al.A review of jet grouting practice and development[J].Arabian journal of geosciences,2018,11(16):459.
[2] WANG Z F,SHEN S L,HO C E,et al.Investigation of fieldinstallation effects of horizontal twin-jet grouting in Shanghai soft soil deposits[J].Canadian geotechnical journal,2013,50(3):288-297.
[3] 张帆.二种先进的高压喷射注浆工艺[J].岩土工程学报,2010,32(S2):406-409.
[4] WANG Z F,SHEN S L,HO C E,et al.Jet grouting practice:an overview[J].Geotechnical engineering,2013,44(4):88-96.
[5] 洪成泼.上海软土地层MJS工法施工及应用研究[D].杭州:浙江大学,2017.
[6] 王建军.某深隧工程下穿运行地铁加固技术[J].施工技术,2020,49(1):109-112.
[7] 夏果夫.咬合桩+MJS工法桩在围护结构缺陷修复中的应用[J].上海建设科技,2020(5):24-27.
[8] 张子新,李佳宇.MJS法地基处理技术综述与应用[J].土木建筑与环境工程,2017,39(6):1-11.
Application of the MJS Method Ultra-long High-pressure Jet Grouting Pile in Deep Foundation Excavation Waterproof Engineering
LIU Chengchi BIAN Ruifan SUI Bodong
(Zhejiang Geology and Mineral Construction Co.,Ltd. School of Civil Engineering,Tongji University)
Abstract: Based on the project of No.10 plot named Ruihong New Town in Shanghai,the application of the MJS method ultra-long high-pressure jet grouting pile in deep foundation excavation waterproof engineering was studied. Combined with the construction principle of the MJS method, the main construction characteristics and key control factors during the construction of the pile in ultra-deep soil layers were summarized. The field test results show that the MJS method ultra-long high-pressure jet grouting piles have good pile quality,the diameter can reach 2. 55 ~ 2. 80 m at the depth of 20 m,and the unconfined compressive strength is more than 1. 3 MPa. The waterproof reinforcement construction has little influence on the surrounding soils. The vertical ground surface displacement is less than 2. 22 mm,and the maximum horizontal displacement of the deep soil at the distance of 6 m from the designed pile boundary is less than 4 mm.
Keywords: deep foundation excavation; high-pressure jet grouting piles; waterproof curtain; MJS method; construction