受限条件下深厚新填土场地桩基及基坑统筹设计

引用文献:

袁运涛 李苏春 韩霜 鲁瑞武. 受限条件下深厚新填土场地桩基及基坑统筹设计[J]. 建筑结构,2022,48(14):131-135.

YUAN Yuntao LI Suchun HAN Shuang LU Ruiwu. Overall design of pile foundation and foundation pit of recent deep filling site under restricted conditions[J]. Building Structure,2022,48(14):131-135.

作者:袁运涛 李苏春 韩霜 鲁瑞武
单位:江苏华岩建设有限公司
摘要:以周边环境要求高、地质条件复杂、非常规施工的某工程为例,详细分析其工程特点。采用正交分析法对桩基及基坑进行统筹设计,以实测结果分析桩基及基坑在开挖过程中的相互影响。结果表明:对下部有较好持力层的深厚新填土场地选用载体桩是合理的,填土厚度、均匀性对载体桩单桩承载力影响不大;先行施工的永久性挡墙锚杆、灌注桩可明显提高基坑的整体稳定性;深厚新填土中采用桩侧压密注浆对提高载体桩抗压效果不明显,但可显著提高水平承载力;基坑开挖前施工的锚杆最大位移及塑性位移均明显大于基坑开挖后施工的锚杆;深层水平位移沿填土深度逐步减小,并在下部黏土顶面附近趋近于零。
关键词:桩基;基坑;统筹设计;深厚填土;载体桩;单桩承载力
作者简介:袁运涛,硕士,高级工程师,主要从事岩土及地下结构工程研究工作,Email:635102933@qq.com。
基金:苏州市建设系统科研项目(2020年度)。
尊敬的用户,本篇文章需要2元,点击支付交费后阅读
参考文献[1] 何全新.利用抗滑桩兼做房屋桩基的一次设计[J].建筑结构,1994,24(11):40-46.
[2] 褚福权,蔡体龙.围护桩兼作地下工程抗浮和外模的尝试[J].地下空间,1996,16(1):48-51,64.
[3] 朱祖华.地下铁道车站人工挖孔矩形支护桩兼作主体结构的设计[J].铁道标准设计,1997,25(2):31-34.
[4] 杨敏,周洪波,杨桦.基坑开挖与临近桩基相互作用分析[J].土木工程学报,2005,52(4):91-96.
[5] 王卫东,翁其平.“两墙合一”设计关键技术问题研究[J].地下空间与工程学报,2005,25(4):574-578.
[6] 宋青君,王卫东,翁其平.“两墙合一”深基坑工程设计中的若干技术问题与对策[J].岩土工程学报,2006,22(S1):1590-1595.
[7] 郑刚,颜志雄,雷华阳,等.基坑开挖对临近桩基影响的实测及有限元数值模拟分析[J].岩土工程学报,2007,29(5):638-643.
[8] 郭晓清.厂房桩基兼作挡墙中的抗滑桩(群)的设计与技术处理[J].建筑结构,2008,38(7):136-137.
[9] 龚晓南,王继成,伍程杰.深基坑开挖卸荷对既有桩基侧摩阻力影响分析[J].湖南大学学报(自然科学版),2014,41(6):70-76.
[10] 俞建霖,徐山岱,龙岩,等.软土地基中基坑内工程桩对开挖性状的影响[J].沈阳建筑大学学报(自然科学版),2020,36(3):474-482.
[11] 郑刚,王琦,张立明.基坑开挖对坑底工程桩性能影响参数分析[J].建筑结构,2015,45(21):63-69.
Overall design of pile foundation and foundation pit of recent deep filling site under restricted conditions
YUAN Yuntao LI Suchun HAN Shuang LU Ruiwu
(Jiangsu Huayan Construction Co., Ltd.)
Abstract: Taking a project with high requirements of surrounding environment, complex geological conditions and unconventional construction as an example, the engineering characteristics were analyzed in detail. Overall design of pile foundation and foundation pit was carried out by orthogonal analysis method, and the interaction between pile foundation and foundation pit in the excavation process was analyzed based on the measured results. The results show that it is reasonable to select piles with ram-compacted for recent deep filling site with better bearing layer. The thickness and uniformity of filling site have little influence on the bearing capacity of piles with ram-compacted. The anchor rod in permanent retaining wall and cast-in-place piles constructed in advance construction can significantly improve the overall stability of the foundation pit. The effect of pile side compaction grouting in recent deep filling site on improving the compressive capacity of piles with ram-compacted were not obvious, but it can significantly improve the horizontal bearing capacity. The maximum displacement and plastic displacement of anchor rod constructed before the excavation of the foundation pit are significantly greater than that of the anchor rod constructed after the excavation of the foundation pit. The deep horizontal displacement decreases gradually along the filling soil depth and tends to zero near the top surface of the lower clay.
Keywords: pile foundation; foundation pit; overall design; deep filling soil; piles with ram-compacted; bearing capacity of single pile
407 0 0
文字:     A-     A+     默认 取消