北京工人体育场施工用钢栈桥设计与监测

引用文献:

黄中营 王猛 刘聪 王怡森. 北京工人体育场施工用钢栈桥设计与监测[J]. 建筑结构,2023,48(06):71-75,25.

HUANG Zhongying WANG Meng LIU Cong WANG Yisen. Design and monitoring of steel trestle for construction of Beijing Workers Stadium[J]. Building Structure,2023,48(06):71-75,25.

作者:黄中营 王猛 刘聪 王怡森
单位:北京建工集团有限责任公司 河北省土木工程灾变控制与灾害应急重点实验室 华北科技学院建筑工程学院
摘要:北京工人体育场工程因基坑占地面积大、工期紧,物资完全依赖塔吊不满足进度要求,设计了一道钢栈桥供运输及施工车辆行驶,便于材料运输及施工,加快施工速度。介绍了钢栈桥整体安装过程,采用MIDAS Gen软件对安装过程进行有限元模拟,验证了钢栈桥的安全性;建立健康监测系统进行荷载试验监测,确保钢栈桥运营期间的可靠性。结果表明,钢栈桥在安装过程和运营期间安全、可靠,能有效抵御车辆的往复荷载。
关键词:北京工人体育场;钢栈桥;荷载试验;有限元模拟;大高差;重荷载;
作者简介:黄中营,学士,高级工程师,主要从事土建施工等方面研究,Email:157266903@qq.com。刘聪,硕士研究生,主要从事结构设计等方面研究,Email:562037015@qq.com。
基金:河北省省级科技计划资助(22375410D)。
尊敬的用户,本篇文章需要2元,点击支付交费后阅读
参考文献[1] 蒋赣猷,郑健,李莘哲.钢栈桥结构设计与有限元分析[J].西部交通科技,2021(12):82-84,123.
[2] 海大鹏,吕政,王小强,等.深厚卵石覆盖层地基的钢栈桥施工技术研究[J].建筑结构,2022,52(S1):3165-3169.
[3] 张玉斌,王云,徐镭.张湾特大桥钢栈桥设计与施工技术[J].建筑结构,2020,50(S1):1153-1155.
[4] 张燕.施工栈桥在深基坑工程中应用技术研究[J].建筑结构,2018,48(S1):783-787.
[5] 左明华.通航河道提升式钢栈桥设计与应用[J].西部交通科技,2022,180(7):101-103,125.
[6] 任东辉,高丕勤.昌平泵站调蓄池工程大型深基坑临时栈桥的设计与施工[J].建筑结构,2008,38(4):48-49,90.
[7] 盛平,张龑华,甄伟,等.北京工人体育场结构改造设计方案及关键技术[J].建筑结构,2021,51(19):1-6.
[8] 田娥,杨正军,李毅,等.大型钢结构工程中临时钢栈桥设计及验算[J].工业建筑,2012,42(9):157-161.
[9] 贾坚,刘传平,张羽.在软土深基坑栈桥上运行铁路列车的安全稳定控制技术[J].岩土工程学报,2012,34(S1):324-329.
[10] 张清华,崔闯,魏川,等.钢桥面板疲劳损伤智能监测与评估系统研究[J].中国公路学报,2018,31(11):66-77,112.
Design and monitoring of steel trestle for construction of Beijing Workers Stadium
HUANG Zhongying WANG Meng LIU Cong WANG Yisen
(Beijing Construction Engineering Group Co., Ltd. Hebei Key Laboratory of Civil Engineering Catastrophe Control and Disaster Emergency Response Architectural Engineering College, North China Institute of Science and Technology)
Abstract: Beijing Workers Stadium project because of the large area foundation pit and tight construction period, relying on the tower crane for materials completely does not meet the schedule requirements. A steel trestle was designed for transportation and construction vehicles, which was convenient for material transportation and construction and speeded up construction speed. The whole installation process of steel trestle was introduced. The finite element simulation of the installation process was carried out by MIDAS Gen software to ensure the safety of steel trestle. The health monitoring system of steel trestle was established to carry out load test and ensure the reliability of trestle project in service period. The results show that the steel trestle is safe and reliable in the installation process and service period, the steel trestle can effectively resist the reciprocating load of vehicles.
Keywords: Beijing Workers Stadium; steel trestle; load test; finite element simulation; large height difference; heavy load